Performing Arts Center at Bonney Lake High School

EMA is working with the Sumner-Bonney Lake School District to plan a new 13,000 square foot Performing Arts Center at Bonney Lake High School. The new facility currently plans to seat at least 550, and will include a stage, side stage, orchestra pit, and green room. There will also be a generously sized lobby for guests during intermissions, as well as pre and post events.

The new performing arts center, located adjacent to the existing Bonney Lake High School, will be the new centerpiece for the campus. The facility has been designed to accommodate 550 people with provisions and elements to serve from elementary level presentations to professional performances. The High School will also take advantage of the large seating area for lectures, testing, and other educational priorities.

Once completed, the new Performing Arts Center at Bonney Lake High School will serve educational needs across the entire district.

Sumner-Bonney Lake School District

Bonney Lake, WA

Construction Phase

Grades 9-12

New Construction

 To Be Completed Spring 2019

15,523 SF

Project Costs

Cost Estimate: $5,236,147
Bid Amount: $9,859,800
Final Cost: $5,468,630
Change Order %: 3.1%