Construction of Collins Elementary is coming along!

According to our original schedule, the roof framing on Zone C was scheduled to begin 10/28-11/11/2019. But as you can see from the images, we began flying in the roof joists on C wing on September 10th.

We discovered that we needed to get Zone C to a point that it can be secured faster with doors, windows, and roof. This is necessary to enhance site security.

Even with pushing ‘C’ wing ahead, our expected substantial completion date is June 30, 2020